More Environment Agency money cuts the council's sea defence bill by £6.5m
Cabinet is asked on 12 November to start the last phase of the Brighton Marina to River Adur scheme. The council's share would fall from £11m to £4.5m.

The council’s share of the cost of new sea defences between Brighton Marina and the mouth of the River Adur is set to drop from £11 million to £4.5 million. The Environment Agency has raised its grant for the scheme from £14 million to £25.9 million, and the Labour-run council’s cabinet will be asked on Thursday 12 November to approve the new funding and start the last phase of building.
The scheme covers about 10km of coast. In Hove, the old timber groynes on the beach between the King Alfred Leisure Centre and Second Avenue are being replaced with new ones that reach further out to sea. Thousands of tonnes of shingle then go in between them to widen the beach, which the council says will absorb wave energy and cut down on stones washed up on to Kings Esplanade. Rock armour has already been laid next to Basin Road South, and a new sea wall built near the Hove Deep Sea Anglers Club.
Brighton & Hove leads the scheme, working with Adur & Worthing Councils, Shoreham Port Authority and the Environment Agency. Phase 3, the one now up for approval, is mostly inside Shoreham Port: repairs to the sea walls, new rock revetments and public paths put back. The contract is worth about £13.5 million and would go out to open tender. The port pays for work on its own assets.
The whole scheme is now forecast to cost £36.5 million. In April 2025 the cabinet raised the council’s funding for this stage from £6.5 million to £11 million, citing rising costs and the need for extra shingle. With the bigger grant, the council’s borrowing falls by £6.5 million, which the report calls “a significant improvement in the affordability of the Scheme”. The report is from Cllr Trevor Muten, the cabinet member for Transport and City Infrastructure.
The catch is time. The Hove work was due to run from late September 2025 to May 2026, and the council’s coastal page now says it should finish around November 2026.
Waste wood from the new groynes is going to the charity Men in Sheds, which makes it into new items to fund its workshops. People working on the scheme have also put in more than 300 volunteer hours, and £1,000 is due to go to homeless charities in the city.
How to get involved
Ask the cabinet a question (opens a new tab)
Written questions from the public for this meeting must be in by 12 noon on Friday 6 November. Democratic Services: democratic.services@brighton-hove.gov.uk, or Raymond Bruce-Cathline on 01273 29 1354
Go along or watch (opens a new tab)
Cabinet meets at 10.30am on Thursday 12 November in the Council Chamber at Hove Town Hall, Norton Road. The public gallery is on the first floor. The meeting may be filmed for the council's website
Read the report (opens a new tab)
The cabinet report sets out the funding, the Phase 3 works and the community work done so far
Sources
- Brighton Marina to River Adur Flood and Coastal Erosion Risk Management (FCERM) Scheme, Cabinet, 12 November 2026 (Brighton & Hove City Council)
- Appendix 1: Social and Community Engagement Delivery (Brighton & Hove City Council)
- Agenda frontsheet, Cabinet, 12 November 2026 (Brighton & Hove City Council)
- Protecting our coast from flooding and coastal erosion (Brighton & Hove City Council)
- Biggest sea defences scheme in Hove on the horizon (Brighton & Hove City Council)
Every fact in this story is checked against these sources. How we work
Spotted a mistake or something we missed?Tell the editor
Thank you. Your note is with the editor.
If you left an email address, we can reply there.